Once restarted, the Reliquias project would deliver approximately 2.2 million oz. of silver-equivalent production annually over a nine-year life, based on estimates presented by a preliminary economic assessment (PEA) earlier this year. Construction of the mine is expected to take 10 months, as all essential infrastructure is already in place.
The PEA estimates the project’s after-tax net present value to be C$85 million at a 5% discount rate, with an after-tax internal rate of return of 51%. The initial capital is estimated at $24.8 million, with a payback period of 1.8 years.
The project currently requires no further environmental clearances as existing permits from previous operations remain fully enforceable. Silver Mountain recently obtained an extension of the main environmental permit, allowing it to operate the mine until 2034.